Lead time and availability for LBSA batteries depend largely on project size and configuration. LBSA keeps stock for common low-voltage items, but high-volume or specially configured high-voltage (HV) systems follow a manufacturing schedule.
Typical Manufacturing Lead Times
For large projects (multi-MW), manufacturing of the battery racks and modules typically takes 3–5 business days. For smaller sites or standard product configurations, LBSA can often manufacture units within 24–48 hours.
What “lead time” includes
The lead times above refer to the manufacturer build window only. Additional time is commonly required for:
- Quality checks & factory testing: end-of-line verification, BMS firmware load and burn-in testing.
- Logistics & delivery: local dispatch, freight booking, and transit to site.
- Custom configuration: specialised rack layouts, bespoke communications or enclosure requirements can add time.
- Permits & site readiness: civil works, electrical infrastructure and access permits influence project start.
Typical project timeline (planning to commissioning)
As a planning guide (times will vary by project):
- Design & quotation: 1–2 weeks (site survey, load analysis, system design).
- Manufacture: 24–48 hours for small orders; 3–5 business days for multi-MW orders (as above).
- Delivery: local deliveries typically 1–7 days depending on location and freight method.
- Installation & commissioning: 1–5 days per rack bank depending on site complexity and integration needs.
Factors that can shorten lead time
- Stock availability: selecting in-stock configurations drastically reduces wait time.
- Standardised designs: avoid bespoke enclosures or unusual communications options when time is critical.
- Early deposit & confirmed PO: speeds up production scheduling.
Recommendations for procurement
- Confirm availability with LBSA sales before issuing purchase orders.
- Plan logistics early (freight, crane/handling, storage) to avoid site delays.
- Allow time for commissioning support and firmware updates—book LBSA commissioning assistance in advance.
Conclusion
LBSA can manufacture smaller systems within 24–48 hours and larger multi-MW projects in 3–5 business days. For accurate project planning, always confirm current stock and lead times with LBSA Sales — and factor in delivery, site preparation, and commissioning when estimating the total project schedule.